Specifications of oil-immersed transformers

Jan 26, 2024

Leave a message

GNEE Steel Oil Immersed Amorphous Alloy Distribution Transformer

There are also many common oil-immersed transformers assembled. Today's economic development is inseparable from electricity, and electricity is inseparable from oil-immersed transformers. Therefore, assembly is more important for oil-immersed transformers. What issues should be paid attention to during the assembly of common oil-immersed transformers? What are the requirements? Let's find out with the editor of the transformer manufacturer:

1. Working hours quota: The comprehensive working days required for body assembly are 21 working days. The work content includes: unpacking inspection, main body in place, body inspection, cleaning of casing, oil pillow and radiator, etc., oil column test, assembly of accessories, production and assembly of pad iron and wheel stopper, supplementary column and the whole assembly after assembly Sealing test, grounding, touch-up paint, etc.

info-428-298

2. Assembly site layout: Overhaul and assembly of power oil-immersed transformers are best carried out in the maintenance room. If there is no maintenance room, you need to choose a temporary assembly site near the foundation platform of the oil-immersed transformer to put the oil-immersed transformer in place. You can also assemble it on-site on the foundation platform. There should be a tent at the outdoor site. The temporary assembly site must be easy to transport, the road should be flat and of sufficient width, the ground should be solid, flat and dry, away from smoke windows and water towers, and the distance from nearby buildings should meet fire protection requirements. After long-distance transportation, oil-immersed transformers will be subject to greater vibrations and require body inspection. The body inspection of oil-immersed transformers is divided into hanging cores and hanging hoods. Regardless of hanging cores or hanging hoods, the inspection contents are the same. Yes, the hanging core inspection should be completed within one working day to speed up the inspection process.

Send Inquiry